Fort Pulaski National Monument - All Documents and Projects

Southeast » Georgia

Listed in the table below are plans or projects and associated documents that have been posted to the public for the selected NPS unit. Click on the project title for more information on the whole project or on the document title for information on the specific document.

For general information, use the 'Park/Unit Information' link to the left to go to the park's main internet page to access park information not related to park planning (for example, park brochures, lodging and campground reservations, and general park information).

Project Title Document Title Review End Project Type
Replace Cockspur Lighthouse Revetment Scoping Newsletter May 07, 2008 Other Maintenance Activities
Replace Cockspur Lighthouse Revetment Environmental Assessment for the Proposed Bank Stabilization at Cockspur Island Lighthouse May 25, 2009 Other Maintenance Activities
Rehabilitation / Replacement of Fort Pulaski Bridge Public Scoping Documents Feb 28, 2011 Repair/Rehabilitation
Rehabilitation / Replacement of Fort Pulaski Bridge Fort Pulaski Bridge EA Feb 02, 2013 Repair/Rehabilitation
Proposal to Increase Entrance Fees at Fort Pulaski National Monument Fort Pulaski Proposed Fee Increase Dec 17, 2014 Fee Collection
Proposal to Increase Entrance Fees at Fort Pulaski National Monument Fort Pulaski Proposed Fee Increase Press Release Dec 17, 2014 Fee Collection
Rehabilitation / Replacement of Fort Pulaski Bridge Fort Pulaski Bridge Environmental Assessment March 2015 Apr 02, 2015 Repair/Rehabilitation
GPC Tybee Transmission Line Structure Replacement Wetlands Statement of Findings Aug 21, 2019 Construction Permit
Proposed Day Use Fee at Lazaretto Creek Area Public Input Wanted for Proposed Fee at Lazaretto Creek Oct 26, 2019 Fee Collection
Remove Roofing, Repair Sheathing, and Install Higher Wind Rated Roofing on Cottage Draft MOA to Resolve Adverse Effect Jan 03, 2020 Cyclic Maintenance
Development Concept Plan and EA for Facilities and Infrastructure at FOPU Fort Pulaski Development Concept Plan Nov 09, 2024 Development Concept Plan/Site Plan
Fort Pulaski National Monument General Management Plan General Management Plan/Wilderness Study/EIS General Management Plan
Rehabilitation / Replacement of Fort Pulaski Bridge Fort Pulaski Bridge Finding of No Significant Impact (FONSI) May 2015 Repair/Rehabilitation
Rehabilitation / Replacement of Fort Pulaski Bridge Finding of No Significant Impact for the Fort Pulaski Bridge Project Repair/Rehabilitation
Replace Cockspur Lighthouse Revetment Cockspur Island Lighthouse FONSI/Errata Sheet/SOF Other Maintenance Activities
* Open for comment.