Project Links
Repair Washed Out Drainage Ditch at Arches HQ Area
Arches National Park » Repair Washed Out Drainage Ditch at Arches HQ Area » Document List
Three inch diameter recycled plastic fence rails will be bolted together into one to two foot high panels eight feet long. The panels will then be partially buried into the inside bank of the ditch to prevent the earth and rock ditch from eroding during flood events. Vegetation will grow up between the logs adding additional stabilization to the bank. The plastic logs will not rot and, by being partially buried and anchored by two vertical logs per panel, will not wash away. The American Conservation Experience crews will be used to do the work. This is repair to an existing structure. The ditch will first be cleaned of overgrowing vegetation which will be placed into a dumpster and hauled away.