Thank you for your interest and comments throughout the Bridalveil Fall Rehabilitation planning process.

* indicates the current step in the planning process
Step 1. Conduct external scoping
Step 2. Refine alternatives
Step 3. Analyze environmental impacts and identify preferred alternative
Step 4. Public review of environmental assessment
Step 5. Analysis of public comment
Step 6. Prepare final plan/decision document
Step 7. Release final plan/decision document to the public *

The Regional Director signed the Bridalveil Fall Rehabilitation Environmental Assessment Finding of No Significant Impact on May 24, 2018. The park plans to begin implementation of the project in summer/fall of 2018 after developing detailed design and construction plans.