The existing culverts are inadequate due to size and location, and have caused the road to act as a dam. The five new culverts will allow greater flow and help reduce the frequency of road closures from the wash overtopping the road.

Proposed Work: The work will include saw cutting 35' of the roadway, installing five 49" x 33" culverts and then backfilling and compacting. This section of the roadway will be compacted dirt up to the elevation of the existing asphalt until sometime in early to late spring, at which point it will be paved. All work will stay within the existing road prism.

Contact Information

Sabrina Henry 435-719-2135