We are pleased to announce that we have completed our conservation planning for forest restoration in the Middle Fork of Lost Man Creek. We have documented our decision to thin second-growth forest stands in the Middle Fork project area to accelerate the restoration of old-growth conditions in a Finding of No Significant Impact (FONSI) Please click on "Document List" to view or download the FONSI

* indicates the current step in the planning process
Step 1. Define purpose and need/develop preliminary alternatives
Step 2. Conduct external scoping
Step 3. Identify environmental impacts and select preferred alternative
Step 4. Prepare draft plan/environmental document
Step 5. Public review of draft plan/environmental document
Step 6. Analysis of public comment
Step 7. Prepare final plan/decision document
Step 8. Release final plan/decision document to the public *