November 2007: Project Summary

June 2008: Environmental Assessment (EA) for 30-day public comment

August 2008: Finding of No Significant Impact (FONSI) with Errata and Statement of Findings for Floodplains signed

Fall 2008 - Spring 2009: Construction period

Easter 2009: Anticipated completion of trail construction and trail opening ceremony