Lakeshore Drive

Rehabilitate Wahweap Access Roads/Lakeshore Drive

Glen Canyon National Recreation Area » Rehabilitate Wahweap Access Roads/Lakeshore Drive » Document List

The National Park Service (NPS) has approved a Finding of No Significant Impact (FONSI) for the planned rehabilitation of Lakeshore Drive in Glen Canyon National Recreation Area (Glen Canyon). The project area is located just north of the Glen Canyon Dam near Page, Arizona. Other than a small portion in Kane County, Utah, the project is located in Coconino County, Arizona.

The NPS plans to rehabilitate, restore, and resurface approximately 5 miles of Lakeshore Drive, 2 miles of Wahweap Boulevard, and 0.3 miles of Wahweap Marina Drive in Glen Canyon. The project will include replacement of damaged concrete and asphalt curb, installation of concrete curb in new locations to address roadway drainage issues, drainage structure improvements, drainage improvements of existing ditches, pullout improvements, removal of existing guardrail, installation of new guardrail, and other safety improvements.

This project is expected to be implemented in phases. During the six months of Phase 1 road rehabilitation tentatively planned for the winter and spring of 2015/2016, the NPS proposes to close the South Entrance and Lakeshore Drive. During this time, access to the Wahweap Marina area will be through the North Entrance. Low power lines will be placed underground to allow large trailered houseboats to use this route. Some of the Wahweap area roads along this route will be temporarily converted to a one-way loop to accommodate the passage of large vehicles and vessels.

An Environmental Assessment (EA) has been prepared in compliance with the National Environmental Policy Act (NEPA) to provide a decision-making framework that 1) analyzes a reasonable range of alternatives to meet project objectives, 2) evaluates potential issues and impacts to park resources and values, and 3) identifies mitigation measures to lessen the degree or extent of adverse impacts. The project also complies with Section 106 of the National Historic Preservation Act and all other applicable laws and regulations.

The EA was available for public review and comment from Friday, March 27, 2015 through Monday, April 27, 2015. The FONSI was signed on June 22, 2015.

Contact Information

Teri Tucker, Assistant Superintendent
Teri_Tucker@nps.gov