Gas main and service replacement work throughout historic district at Lincoln Home NHS
Lincoln Home National Historic Site » Gas main and service replacement work throughout historic district at Lincoln Home NHS » Document List
The current steel pipes will be replaced with polyethylene and the meters inside the buildings will be replaced. Where the lines come into the buildings, service holes up to 2' x 2' will be created along the foundations.
Bore pits will be created at the intersection of Capitol Avenue and both east and west alleys in the park. A pit will also be dug in the alley between the Dean House (HS-13) and the Visitor Center (S-31) to service both buildings. Pits will also be needed directly east of the Conference Center (HS-30), Lincoln Home Carriage House (HS-01A), and the Arnold House (HS-20) in the alley.
Ameren has agreed to excavate all the bore pits at the same time so that an archeologist under contract with the park, can monitor the excavation. Ameren will then place "road plates" over the pits to allow for general auto use. When completed, the pits will be filled with sand and flowable fill and topped with either asphalt or concrete to match the surrounding roadway.
Attached images were taken with the photographer standing about where the pit would be created, looking toward the building where the gas line would be bored.