Scoping is the first step to involve the public in the environmental analysis process. The following steps outline the process the park will follow to create a Motorized Vehicle Access Plan/ Environmental Assessment and final rule. A rule is required under Executive Order 11989.

* indicates the current step in the planning process
Step 1. Internal Scoping (October 2007)
Step 2. Public Scoping (June 2008)
Step 3. Alternatives Development (Fall 2008 - Spring 2009)
Step 4. Preparation of Plan/ Environmental Assessment (Summer 2009 - Summer 2010)
Step 5. Public Comment on Plan/ Environmental Assessment (Nov 17, 2010 - Jan 15, 2011) *
Step 6. Public Comment on Draft Rule (Spring 2011)
Step 7. Final Decision Document and Final Rule (Summer 2011)

After the final decision document is signed, Curecanti National Recreation Area can implement the plan and final rule.