Canaveral National Seashore's general management plan process is expected to take several years to complete. A summary of the process and anticipated time frame is presented below. You will have opportunities to share ideas and comments throughout the process.

* indicates the current step in the planning process
Step 1. Initiate Project, Summer 2003
Step 2. Define Planning Context and Foundation, Fall 2003 - Winter 2006
Step 3. Publish Alternatives Newsletter, Spring 2007 *
Step 4. Publish Draft Document, Fall 2008
Step 5. Publish Final Document, Winter 2009 - 2010
Step 6. Implement the Approved Plan, Spring 2010 and Beyond