Billings, MT - Lovell to Yellowtail Transmission Line Rebuild
 
Date Start Time End Time Time Zone Location
Jul 8, 2008 4:00 PM 7:00 PM Montana Fish Wildlife and Parks
2300 Lake Elmo Drive
Billings, Montana
406-247-2940

Western Area Power Administration will be conducting three public scoping meetings near the project area to present the project and gather public input regarding issues and concerns.


 
Description:
This project proposes to rebuild the Lovell to Yellowtail No.1 and No. 2 115-kV transmission lines and to upgrade the lines to be capable of operating at 230-kV.

The rebuild of the transmission lines will occur in 2 phases. Phase I will only include the transmission lines within the NRA boundary, and a short segment crossing BLM land. Phase II will include the rebuild of the transmission lines located outside the NRA boundary.

Meeting Directions/Instructions:


Little Bighorn Battlefield National Monument - Lovell-Yellowtail Transmisison Line Rebuild
 
Date Start Time End Time Time Zone Location
Jul 9, 2008 4:00 PM 7:00 PM Little Bighorn Battlefield National Monument
P.O. Box 39
Crow Agency, Montana
406 638-3204
Western Area Power Administration will be conducting three public scoping meetings near the project area to present the project and gather public input regarding issues and concerns.
 
Description:
This project proposes to rebuild the Lovell to Yellowtail No.1 and No. 2 115-kV transmission lines and to upgrade the lines to be capable of operating at 230-kV.

The rebuild of the transmission lines will occur in 2 phases. Phase I will only include the transmission lines within the NRA boundary, and a short segment crossing BLM land. Phase II will include the rebuild of the transmission lines located outside the NRA boundary.


Meeting Directions/Instructions:
Exit 510 off I-90, Hiway 212, Crow Agency, Montana

Bighorn Canyon NRA - Lovell-Yellowtail Transmission Line Rebuild
 
Date Start Time End Time Time Zone Location
Jul 10, 2008 4:00 PM 7:00 PM Bighorn Canyon NRA Visotor Center
20 Howay 14A East
Lovell, Wyoming
307 548-2251
Western Area Power Administration will be conducting three public scoping meetings near the project area to present the project and gather public input regarding issues and concerns.
 
Description:
This project proposes to rebuild the Lovell to Yellowtail No.1 and No. 2 115-kV transmission lines and to upgrade the lines to be capable of operating at 230-kV.

The rebuild of the transmission lines will occur in 2 phases. Phase I will only include the transmission lines within the NRA boundary, and a short segment crossing BLM land. Phase II will include the rebuild of the transmission lines located outside the NRA boundary.


Meeting Directions/Instructions: