Big Spring - Relocate Transformer and Control Panel for Sewage Lift Stations

Ozark National Scenic Riverways » Big Spring - Relocate Transformer and Control Panel for Sewage Lift Stations » Document List

Two transformers and control panels that service lift stations for the sewage system in the Big Springs area will be relocated to the existing locations of the disconnect panels. The relocation is required to reduce the number of pumps going bad due to the voltage drop caused by the excessive distance in the line from the transformers and control panel.

Two 3'x5'x1' concrete pads will be placed at the existing disconnect panels with new posts to support the transformer, control and disconnect panel. All work is within a developed area and does not involve any historic structures.