Alley Spring and Powder Mill- Vegetative Bank Stabilization

Ozark National Scenic Riverways » Alley Spring and Powder Mill- Vegetative Bank Stabilization

Repair approx. 1500 linear feet of Vegetative Bank Stabilization at Alley Spring and Powder Mill areas. 1. Cut willow stakes 2-3" X 3-4' in length from nearby location. 2. Drive willow stakes in bank tow (requires portable jack hammer or demolition hammer). 3. Plant bare root sycamore seedlings on the bank above the toe. 4. Plant appropriate native species on a 30 foot wide strip along the cut bank.