Big Spring - Relocate Transformer and Control Panel for Sewage Lift Stations


Two transformers and control panels that service lift stations for the sewage system in the Big Springs area will be relocated to the existing locations of the disconnect panels. The relocation is required to reduce the number of pumps going bad due to the voltage drop caused by the excessive distance in the line from the transformers and control panel.

Two 3'x5'x1' concrete pads will be placed at the existing disconnect panels with new posts to support the transformer, control and disconnect panel. All work is within a developed area and does not involve any historic structures.

 
Document Content:
Disclaimer: Links within the above document(s) were valid as of the date published.
Note: Some of the files may be in PDF format and can be viewed using the Adobe Acrobat Reader software. You may download a free copy of from Adobe Systems.