Finding of No Significant Impact North Fork Lost Man Creek Bridge


The Finding of No Significant Impact for the North Fork Lost Man Creek Bridge project describes the conservation planning and impact analyses for removing undersized failing culverts that block passage for anadromous fish to upstream spawning habitat. The culverts will be replaced by a bridge. Work is expected to begin on September 16, 2009. The Lost Man Creek Bike Trail will be closed for about a month while heavy equipment work is underway. The project is scheduled for completion by spring 2010.
 
Document Content:
Finding of No Significant Impact   (1.4 MB, PDF file)
Disclaimer: Links within the above document(s) were valid as of the date published.
Note: Some of the files may be in PDF format and can be viewed using the Adobe Acrobat Reader software. You may download a free copy of from Adobe Systems.