Finding of No Significant Impact North Fork Lost Man Creek Bridge
The Finding of No Significant Impact for the North Fork Lost Man Creek Bridge project describes the conservation planning and impact analyses for removing undersized failing culverts that block passage for anadromous fish to upstream spawning habitat. The culverts will be replaced by a bridge. Work is expected to begin on September 16, 2009. The Lost Man Creek Bike Trail will be closed for about a month while heavy equipment work is underway. The project is scheduled for completion by spring 2010.