The National Environmental Protection Act (NEPA) sets forth a process for including public input into significant planning projects conducted by federal agencies. Steps completed in this process thus far on the Wilderness & Backcountry Stewardship Plan are:

* indicates the current step in the planning process
Step 1. Define purpose and need/develop preliminary alternatives
Step 2. Conduct external scoping
Step 3. Refine alternatives
Step 4. Identify environmental impacts and select preferred alternative
Step 5. Prepare draft plan/environmental document *

The monument is currently finalizing a draft document for public review.