The NPS is seeking public input to guide the development of a Site Management Plan for Petroglyph Point at Lava Beds National Monument. The plan is in the early stages of development and the park is seeking feedback from the public and stakeholders.

Steps in the planning process are outlined below.


* indicates the current step in the planning process
Step 1. Develop preliminary concepts and describe potential solutions (Fall 2024).
Step 2. Develop alternatives. The planning team will develop a proposed action and reasonable alternatives based on public input, safety considerations, visitor opportunities, and resource analysis (Winter 2024-2025).
Step 3. Prepare and distribute site management plan. You will have an opportunity to comment on the plan and environmental analysis (anticipated Summer 2025). *
Step 4. Distribute the decision document and prepare to implement the plan (Summer-Fall 2025).