Green River Crossing Environmental Assessment/Assessment of Effect
February 18, 2011 public meeting announcement and press release
February/March 2011 public meetings in Brownsville and Lincoln
February 18, 2011 beginning of public comment period
March 20, 2011 close of public comment period
November 2011 decision document is approved
February 18, 2011 public meeting announcement and press release
February/March 2011 public meetings in Brownsville and Lincoln
February 18, 2011 beginning of public comment period
March 20, 2011 close of public comment period
November 2011 decision document is approved